A balance-beam/equalizing arrangement belongs in the design comparison when the real problem is inter-wheel load redistribution on uneven floors — the cited evaluation cue is heavy AGVs above 2 t with large unloaded-to-loaded differences. Spring forks and cushion treads cushion impact and noise; they do not equalize the static load split between wheels.
Wheel contact alone proves nothing: require per-wheel load calculations, route-surveyed articulation demand, and logged crossing tests before you accept any quote.
Decide whether an equalizer is even in your comparison set
Start by separating the two problems, because quotations often mix them up. A spring suspension fork lets the axle rise against a spring on impact.
A cushion tread compresses a few millimetres to absorb minor unevenness and noise. Both cushion; neither redistributes the static load between wheels3.
A balance beam (equalizing or rocker beam) is a pivoting seesaw linkage coupling typically two wheels. One rises as the other lowers, keeping wheels in floor contact and redistributing load within the mechanism's movement range19.
It was developed specifically for heavy-duty AGVs facing uneven floors and large unloaded-to-loaded differences19. If your problem is impact protection on rough or jointed floors, spring-loaded casters may be the right tool.
If it is four-wheel load imbalance, they are not3. For heavy AGVs carrying more than 2 metric tons on uneven floors with a wide load range, one AGV-suspension supplier suggests a balance-beam layout is worth including in the initial design comparison.
This is explicitly a starting point for evaluation, not an automatic rule19. Against a rigid fixed mount, the equalizer offers mechanism travel that redistributes support motion.
A rigid mount has none. You must prove the worst-case wheel loads, including a possibly unloaded wheel, before selection2.
Check which problem your own platform actually has before you solicit quotes.
Derive the articulation demand from your actual route, not the floor certificate
Before you shortlist any arrangement, state the height differential it must bridge in the wheel path. A floor compliant with DIN 18202 can still contain a difficult local transition.
ASTM E1155 statistical averages can conceal a problematic wheel path. So survey the elevations along the contracted route and model relative wheel displacement instead of copying a flatness number2.
For expansion joints and trench plates, record step height, gap width, edge shape and crossing angle where the vehicle actually crosses. Then ask for loaded and tare crossing tests at agreed speeds2.
No source in this set gives a maximum bridging height differential for a balance-beam arrangement. Two neighbouring figures exist but with stated limits.
One AGV drive-wheel suspension patent specifies vertical travel accommodating about a 5% slope change (~3 degrees)10. This is a patent embodiment, not a spec16.
And 50–75 mm adjustment ranges apply to adjustable-height leveling casters, not equalizer beams15. Treat both as request-and-confirm values only, and derive your own requirement from the surveyed route2.
Ask each supplier to confirm the bridging height against your measured crossings, not against a catalogue figure.
Reject 'wheels stay in contact' as the justification — demand per-wheel loads
Maintaining wheel contact does not automatically guarantee sufficient traction or equal loading. The load split depends on beam geometry and wheel arrangement, and the driven wheel needs enough load without exceeding its rating19.
So ask for per-wheel reactions calculated for each configuration — empty, nominal payload and worst permitted center of gravity. Total mass divided by wheel count is not an acceptable substitute.
Frame deflection, preload, offset top-modules and floor levelness create unequal reactions. One source notes a wheel structurally rated 700 kg may carry only 250 kg normal load in the configured vehicle, and that actual normal load is the traction-relevant value11.
For uncoupled four-wheel layouts, the documented sizing approach divides total weight by one fewer wheel than installed, then applies a safety factor. It is 1.3–1.5 per some sources for uneven force distribution, and 1.25–1.5 per a vendor source for dynamic use over thresholds and ramps18.
Those formulas use different conditions and bases and are not interchangeable. You should pick one convention and state it explicitly in the RFQ rather than letting the supplier blend them18.
Specify the traction tests your motion directions actually need
Unequal wheel load matters more on a self-propelled platform than on towed equipment. One saturated wheel corrupts the intended force vector, and no controller authority can create adhesion the contact patch lacks11.
Validation should measure left and right wheel reactions, plus current and wheel-speed mismatch during straight launches, curves and pivots11. If your platform is omnidirectional, traction must be tested across every direction the application uses.
That means lateral translation, diagonal motion and translation-plus-rotation — not only forward travel, since force and slip behaviour differ by direction11. On differential platforms, pivots deserve particular attention.
A vehicle that launches straight can still current-limit or slip during a loaded zero-radius turn11. You should match the test list to your route, then attach it to the RFQ as an acceptance requirement.
Build the supplier evidence list before you order
Verification is proven by measurement on the real route geometry, not by catalog ratings. ISO 22883:2004 / UNI EN 12532 dynamic wheel testing (1.1 m/s, 500 obstacles, obstacle height 5% of wheel diameter for elastic treads and 2.5% for rigid treads, 20±10 °C) gives a citable basis for the wheels themselves10.
It supplies no numeric equalizer pass criterion, so you set that with the supplier, taking the most conservative condition where data differs10. Before you sign anything, ask each bidder for:
- ✓Individual static wheel reactions per configuration (empty, nominal, worst CG) and the method used to establish them
- ✓Joint and depression crossing tests with wheel-load logging, loaded and tare, at agreed speeds
- ✓Route-specific ramp traversal and stopping evidence, including grade, crest geometry and break-over clearance
- ✓Minimum driven-wheel load in the worst tolerance combinations
- ✓Adhesion test method and boundary surface conditions; grade capability stated by load, direction, speed, duration and restart condition
- ✓Instrumented test records for nominal, boundary and repeated-duty scenarios
- ✓Configuration-controlled acceptance limits with revalidation triggers
Write the arrangement-level configuration parameters into the RFQ
For a rocker/equalizer link, preload is set mainly by geometry and any added spring, and the arrangement requires separate damping if needed. The sourcing checks named for it are coupling behaviour, pivot wear, clearances and support-load limits2.
Specify pivot geometry, degrees of freedom, damping provision and coupled-wheel pairing explicitly, and verify each against your surveyed route2. The evidence names these parameters but supplies no industry-standard values for beam length or ratio, pivot bearing type, mounting height or allowable beam angle.
You must define and confirm them with your supplier. The one travel figure available is a patent embodiment specifying travel accommodating about a 5% slope change (~3°)10.
Treat it as a request-and-confirm value, not a specification16.
Choose the commercial route: trial order vs custom design
No source in this set gives a cost delta between an equalizer bogie and spring-loaded casters. Price that difference per quote rather than assuming it13,28.
Commercial terms vary by supplier and must be confirmed. One caster manufacturer states it supports low-MOQ trial orders, 2–4 week standard and 3–5 week custom lead times, sampling in 5–7 days standard and 15–30 days custom.
And load testing per batch with test reports available. That is that supplier's policy, not an industry norm13.
Ask every bidder for their MOQ, standard vs custom lead times, per-batch load-test policy and pivot-bearing maintenance scope. A custom beam design changes both MOQ and lead time, and no source quantifies that threshold13,28.
Lock the disputed figures into the RFQ before you compare quotes
Two sizing figures conflict across sources, and both land in your RFQ. State which convention applies in writing; otherwise an undersized or oversized design can be justified after the fact with whichever number suited it.
| Disputed figure with unit | One source reports | Another reports | What the buyer should do |
|---|---|---|---|
| 24/7 duty-cycle load de-rate (% vs 8 hr/day) | 30–40% | 25–33% (vendor-tier source) | Pick one de-rate matching your duty and state it in the RFQ |
| Uneven-distribution safety factor (–) | 1.3–1.5 | 1.25–1.5 for dynamic threshold/ramp use | Choose one formula and its stated conditions; do not blend them |
Before you request a quote
- Public sources do not settle this — put it to the supplier: equalizer effective load-split tolerance (e.g. a ±X% load-share figure) — ask the supplier to state and accept one.
- Public sources do not settle this — put it to the supplier: maximum bridging height differential (mm) of a balance-beam arrangement, plus beam length/ratio, pivot bearing type, mounting height and allowable beam angle — no source publishes these; request them as supplier-confirmed values.
- Public sources do not settle this — put it to the supplier: pivot friction/breakaway torque and any pivot-bearing maintenance interval — request both.
- Match the supplier documentation to your application and destination market before approval.
- Request a written quote with price basis, MOQ, tooling, payment terms and production lead time.
- Public sources do not settle this — put it to the supplier: aGV navigation tolerance and slip/steering behaviour figures with an equalizer arrangement — no numbers in this set; ask for navigation and slip test data on your route.
- Public sources do not settle this — put it to the supplier: which wheels are coupled in a multi-wheel equalizer layout (pairing geometry) beyond the two-wheel seesaw description — confirm the bogie pairing for your wheel count.
- Public sources do not settle this — put it to the supplier: the >2 t payload cue and the ~3°/5% travel figure come from a vendor article and a patent document respectively; neither is an industry-wide rule or a commercially available product spec — treat both as starting points to confirm with your own supplier.
Sources · 10
- 2amrdriveunit.comUnclassified source2026-10
- 3globe-caster.comIndustry peer technical page2026-11
- 10elesa.comManufacturer technical documentation
- 11globalsupplychainbriefing.comUnclassified source
- 13chuancaster.comUnclassified source2026-09
- 15infordcaster.comManufacturer technical documentation2026-04
- 16patents.google.comUnclassified source2026-11
- 18skt1m.comUnclassified source
- 19honpine.comUnclassified source2026-10
- 28gtsetu.comUnclassified source2026-06
Technical references cited for verifiability — not supplier recommendations.Browse the research library.